Dry mortar packaging machine installation is complete, the next is the test run, so what are the precautions before running it, the
1, before starting the machine should be the following necessary checks: check the tightening of the bolts in each ministry; the coupling seal of the inlet; whether the location of the outlet is appropriate; check whether the motor wiring is correct.
2.Turn on the power switch: no-load test run; test run time should not be less than 4 hours, during this time the following should be observed: smooth and rapid start, stable vibration, no abnormal noise and friction sound, no material leakage, bearing temperature rise does not exceed 40 ℃, otherwise it should be stopped to check the reasons.